2015's first uhv allowed to start building power equipment companies benefi -ag九游会官方网站

2015's first uhv allowed to start building power equipment companies benefitdate:2016-10-25     hot:1289

learned from the national grid, the national development and reform commission on january 16, kusakabe document, agreed to build mengxi - tianjin south 1000 kv uhv ac power transmission project. this is the first approved in 2015 uhv lines, static investment 17.07 billion yuan.
state grid chairman, party secretary liu zhenya, earlier this year, has said uhv project has entered a new phase of large-scale construction and accelerate the development of the national network this year approved plans to start the construction of "six post eight straight" total 14 power lines, much higher than the last year's "six cross the straight" program.


accelerate the construction of uhv
national development and reform commission recently issued the "national development and reform commission on mengxi - approval of tianjin south 1000 kv uhv ac transmission project approval" marks the current eight years after the successful completion of the preliminary work, full access to the project starts construction phase.


mengxi - tianjin south 1000 kv uhv ac project will be built in west inner mongolia, shanxi province, west beijing, tianjin southern 4 1000 kv substation, the new transformer capacity of 24 million kva, the new mengxi - shanxi province - beijing west - south tianjin double back 1000 kv transmission line project, the line length of 2 × 608 kilometers, static investment 17.07 billion yuan.


according to reports, west inner mongolia - tianjin south 1000 kv uhv ac power transmission project is an important part of the state grid corporation plans to build "three vertical and three horizontal" backbone grid of uhv. january 16, the state grid corporation of video conferencing, to handle the project along the first land clearance and start preparations for a special deployment.


mengxi - tianjin construction engineering for the promotion of south west inner mongolia, northern shanxi energy base development and speed inner mongolia, shanxi energy advantages into economic advantages, to meet the demand of beijing, tianjin region land load growth, the implementation of national air pollution control action plan with significance


shanxi, where mengxi ordos [funds 0.23% research report] are one of china's "twelfth five-year plan" to determine the five largest integrated energy base. west inner mongolia has proven coal reserves of about 193 billion tons, the largest support new coal power installed capacity 120 million kilowatts. but the lack of large-capacity, long-distance transmission channel is always mengxi electric power in the bottleneck. shanxi is expected to "twelve five" will add 20 million kilowatts of low calorific value coal, mainly in northern shanxi, jinzhong, the construction of this urgent need delivery channels to achieve large-scale coal resource utilization.

网站地图